Concrete Delays Construction of New Elementary School ; the Underground Debris Costs About $60,000 Per Day to Remove.
Dayton Daily News › July 21, 2010
Linked as:
Dayton Daily News › July 21, 2010
Linked as:Summary
HUBER HEIGHTS -- Large amounts of concrete, rebar and debris discovered underground at the site of the new Wright Brothers Elementary School has already led to nearly $350,000 in unexpected costs and set the project back by between two to four weeks.
Construction manager Daniel Brown said removing the subterranean concrete costs about $60,000 per day, and it is unknown how much debris remains.See the full content of this document
Extract
Concrete Delays Construction of New Elementary School ; the Underground Debris Costs About $60,000 Per Day to Remove.
The site, located behind Menlo Park and Kitty Hawk elementary schools, was mo...
See the full content of this document
Sponsored links
ver las páginas en versión mobile | web
ver las páginas en versión mobile | web
© Copyright 2012, vLex. All Rights Reserved.
Contents in vLex United States
Explore vLex
For Professionals
For Partners
Company
Other documents:
Wireless technology a new generation of communication from cell phones to PD... | Correction policy. | ACLJ Files Federal Suit Against City of St Paul Minnesota for Unconstitutional Ordinance Targeting Pro-Life Message. | no agreement by freeport-mcmoran copper & gold inc. to divest shares in pt freeport indonesia. | sentencia nº 4240 de consiglio di stato august 26 2009 | Sentencia nº 5377 de Consiglio di Stato, October 28, 2009 | Sentencia nº 6091 de Consiglio di Stato, November 18, 2008 | decisión de tribunal cuarto de primera instancia de sustanciación mediación y ejecución del nuevo régimen y régimen procesal transitorio de...